Percent of Code Complete

LOC complete Week 1Week 2Week 3Week 4Week 5 Week 6 Week 7 Week 8 Week 9 Total
Actual 202 0 568 -36 0 0 12 436 58 1240
Actual To Date 202 202 770 734 734 734 746 1182 1240 1240
Planned 202 202 400 100 0 0 12 350 40 1146
Planned To Date 202 202 602 702 734 734 746 1106 1146 1146


Percent of Defects Found

Defects Found Week 1Week 2Week 3Week 4Week 5 Week 6 Week 7 Week 8 Week 9 Total
Actual 1 0 4 5 2 0 1 17 1 31
To Date 1 1 5 9 12 12 14 30 31 31
Planned** 10 0 28 0 0 0 0 21 2 61

**Recalculated in accordance with the project plan
Stage 2: Defect Tracking

Found 19
Expected 23
Percent 82.6


Percent of Defects Fixed

Defects Fixed Week 1Week 2Week 3Week 4Week 5 Week 6 Week 7 Week 8 Week 9 Total
% 100 100 100 85.7 66.7 66.7 70 83 92 98


Percent of System Tests Passed

System Tests Week 1Week 2Week 3Week 4Week 5 Week 6 Week 7 Week 8 Week 9 Total
Written 0 0 0 7 (non) 9 9 14 15 22 22
Passed 0 0 0 7 (non) 9 9 9 14 22 22


Percent of Resources Used

Team MemberPlannedWeek 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9Total
Jamie 8 5.25 8.5 10.25 14 15 7.25 9.25 9 8 86.5
Terence 8 6 6 8 16 16 7 8 6 6 79
Bill 8 5.5 2 7 20 7 3 6 11 6 67.5
Brian 8 4 5.75 7.25 9.25 5.5 5.25 11.5 4.5 6 59
Jim 8 4 3 8 14.8 12 8 20 8 9 94.8
Total 40 24.75 25.25 40.5 74.05 55.5 30.5 54.75 38.5 35 386.8
% of Planned 100 61.8 63.1 101.3 185.1 138.75 76.25 136.9 96.25 87.5 107.4


To Date Resources Used

Week 1Week 2Week 3Week 4Week 5Week 6Week 7Week 8Week 9
To Date Actual 24.75 50 93.3 167.4 222.9 253.4 305.3 353.8 386.8
To Date Planned 40 80 120 160 200 240 280 320 360
To Date %Actual 6.9 12.5 23.1 41.8 55.7 63.3 76.3 88.4 97.2
To Date %Planned 10 20 30 40 50 60 70 80 90


Batting Average

Action Items Week 1Week 2Week 3Week 4Week 5 Week 6 Week 7 Week 8 Week 9
Completed on time 9 10 8 18 5 9 23 15 13
To Date 9 19 27 45 50 59 82 97 110
Due 10 13 8 19 24 10 25 23 15
To Date 10 23 31 50 55 65 90 113 128
%ontime 90 82.6 87.1 90 90.9 90.7 91.1 86 86

*Missing data from 1+ group member(s)