Project Visibility Calculations

Days Ahead of Schedule

currently -1 days ahead of schedule

Percent of Code Complete

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Actual To Date 175 180 283 531 531 556 624 708 1278
Planned To Date 175 275 375 475 550 625 700 800 1000
% of Planned 100 65.5 75.5 112 96.5 89 89 88.5 127.8

Percent of Defects Found

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Actual 0 2 2 10 4 2 4 5 2
|-> To Date 0 2 4 14 18 20 24 29 57
Planned 3 3 3 3 3 3 3 3 3
|-> To Date 3 6 9 12 15 18 21 24 63
% of Planned 0 33 44 117 120 111 114 121 90

Percent of Resources Used

Planned: 8 * 5 = 40

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Aaron 8 8 12 9 16 8 14 18 17
Brian 12 10 10 10 14 8 9 15 15
Clovas 10 10 8 14 10 7 9 12 12
Michael 6 8 6 6 9 4 11 10 10
Tyler 8 8 10 10 12 8 8 15 15
Total 44 44 46 49 61 35 51 70 69
% of Planned 110 110 115 123 152 87 127 175 172

To Date Resources Used

Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
To Date
Actual
44 88 134 183 244 279 330 400 469
To Date
Planned
40 80 120 160 200 240 280 320 360
To Date
%Planned
110 110 112 114 122 116 118 125 130

Batting Average

Action Items Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9
Completed on time 8 11 12 24 10 6 5 10 17
|-> To Date 8 19 31 55 34 40 45 55 72
Due 8 12 14 24 10 6 8 12 17
|-> To Date 8 20 34 58 34 40 48 60 77
% on Time 100 95 91 95 100 100 94 92 94

Document History