Stage 2.0 Integration Plan


FRIDAY

- Inspections Done By Midnight (Everyone) - Merge Stage 1.1 code into Stage 2.0 (Mark)

SATURDAY

- Work on Defect Repair from Code Inspections (Everyone)

SUNDAY

- Complete Defect Repair from Code Inspections (Everyone)


INTEGRATION STARTS

Remember:

- Unit Test your code before committing!\par

Procedure:

Morning: Person1 Commit

Afternoon: Person2 Commit

Evening(7pm): Richard System Testing

Night(9pm): Fix Code (If necessary)

- Everyone will be allocated a time slot to commit and get your code to compile. NO ONE else will be allowed to commit during another person's time allocation.

- Ideally two people are assigned to commit each day, one in the morning and one in the afternoon. However you can negotiate with your "partner for the day" what times work best for you to commit during that day. COMMITTING MUST be done before 7pm so that Richard can System Test.

- Richard will System Test the newly commited code at 7pm (MTW) and let Paul and the person assigned to the module know if code fails System Tests and needs to be REWORKED via phone or email by 9pm that night.

- If code fails System Testing, then the person assigned to the module will have from 9pm until 6am the next morning to get their code to pass the System Tests.

TIME SLOTS

WEEKDAYPERSONTIMEsLOT
MONDAY Paul 6am-12pm
Ian12pm-7pm
TUESDAY Steph6am-3pm
Tracy3pm-7pm
WEDNESDAY Richard 6am-12pm
Mark12pm-7pm

THURSDAY

- Post Integration Meeting