Project Vision: Create a Quality Code Formatter, which Aids the Customer in More Efficient Code Development, while Abiding by Team and Customer Expectations [ Philosophy ]
| Days ahead of Schedule | 0 |
| Lines of Code Complete | 743 |
| Percent of Code Complete (Actual/Planned) | 100% / 100% |
| Percent of Resources Used (Actual/Planned) | 109.8% / 100.00% |
| Batting Average | 93% |
| Task Completed (Both 308/309) | 420 / 425 |
_Announcements_
* FINAL QA Meeting in CSL Sunday 6/1/08 2pm
* Stage 2 Acceptance Meeting 6/2/08 7pm in lab
* Integration Plan Posted under Project Planning
* Stage 1.1 Release SUCCESS!
* Stage 2 due June 3rd
* We got accepted!!! - April 28th
* Acceptance Meeting 4/28/08 7pm in lab
* Stage 1 due April 29th
_About Our Team_
| Contact Info | Team Expectations | Job Descriptions | Team Photo |